NEWS

(12/01/2014 / sha)

Valmet & Nokianvirran Energia: LOI regarding boiler plant delivery

Valmet and Nokianvirran Energia Oy have signed a letter of intent for a delivery of a biomass-fired boiler plant to a new steam heating station in Nokia, Finland. The new heating station will supply process steam to SCA Hygiene Products' paper mill, Nokian Tyres' factory, and district heat to Leppäkosken Sähkö's customers.

The investment enables the currently used natural gas to be replaced with more cost efficient biofuels, such as forest residue and wood chips. In addition, it is possible to utilize peat and sludge from the paper mill.

The installation work is scheduled to start in May 2015. The start-up of steam production is scheduled for the spring of 2016. The total value of the investment by Nokianvirran Energia is approximatelyEUR 45 million, out of which the share of Valmet's delivery is slightly more than a half.